Survey (Project) Factors

 

 

 

 

Project Factors determine how TPC relates grid positions (coordinates) to geodetic positions (latitude/longitude)..

To access the survey information for the current survey do one of the following:

•From the desktop menu choose Tools | Survey Information and select the Project Factors tab.

•From the Tasks manager, left-click 'Edit Survey Information...' in the Survey Information panel and select the Project Factors tab.


Mapping Angle

The convergence or mapping angle that relates grid directions to geodetic directions for the project.

This is applied only when you select the direction type True Bearing (project mapping angle x°xx'xx").

The Mapping Angle can be computed from the Project Location, in which case TPC uses the Convergence of the project location, based on the current CRS.


Combined Factor

The scale factor that relates grid distance to geodetic distance for the project.

This is applied only when you select the distance type Ground Distance (Combined factor x.xxxxxx).

The Combined Factor can be computed from the Project Location, in which case TPC combines the elevation factor and the grid factor (if a CRS is selected).

You can enter an equation in this field to compute the factor you want.  For example, entering the equation 1/2 would produce the factor 0.5.


Project Location

You can enter a project location in the survey's Project Factors dialog.

TPC uses the project location in a number of ways.

•It can compute the Mapping Angle to used for the project.

•It can compute the Combined Factor used for the project.

•It can be used as the Base Point in the Coordinate Conversion routine, scaling all points towards or away from it.  This routine easily converts coordinates between grid and ground.

•If you select either the ground distance or geodetic distance options which are based on project elevation, TPC assigns the project elevation to any new survey points it creates.


Elevation

The average project elevation in feet (if survey units are feet or chains) or meters (if survey units are meters).

This is applied only when you select the distance type Ground Dist (at project elevation xxxx.xx) and Geo Dist (at project elevation xxxx.xx).

Beginning in TPC Desktop 2011, if you specify a project elevation and set the default distance type to geodetic or ground distance at project elevation, the default elevation for any new survey points you create will be the project elevation.


Preferences

Select a default Distance and Direction type for the survey.