A legal description is written for a traverse, based on its data and configuration.

The Legal Description report converts the traverse data into a legal description using the following rules.

•TPC uses the control points in the traverse to determine the sequence of calls.

•The legal description accounts for curves and spirals (i.e., thence arc length along a curve to the right, the chord of which bears …).

•Side shots can be included as a reference (i.e., said point bears direction and distance from a description).

•Distance and Direction types are determined by the traverse format, as are units.

•Descriptions can be included but point labels cannot.

•Options like Decimal, Units and Abbreviate N, S, E, W let you customize the legal description.

•You can include area and predefined closing text.

•Legal Descriptions can be further edited in the Report View.


Example Traverse and Legal Description

The following simple example shows how TPC converts a wetland boundary into a legal description.

[ Traverse data ]

Point    Description    Bearing       Grid Dist  Northing     Easting
 WL22    WETLAND 7                               6258.495     5588.231
 WL23    WETLAND 7      S59°29'54"E   15.19      6250.784     5601.321
 WL24    WETLAND 7      S7°36'41"W    21.40      6229.576     5598.487
 WL25    WETLAND 7      N63°33'07"W   17.99      6237.590     5582.376
 WL26    WETLAND 7      N5°09'48"W    13.51      6251.042     5581.161
 WL22    WETLAND 7      N43°29'21"E   10.27      6258.495     5588.231

[ Legal Description ]

Commencing at the True Point of Beginning being a WETLAND 7;
Thence S59°29'54"E for 15.19 Feet to a WETLAND 7;
Thence S7°36'41"W for 21.34 Feet to a WETLAND 7;
Thence N63°33'07"W for 17.99 Feet to a WETLAND 7;
Thence N5°09'48"W for 13.51 Feet to a WETLAND 7;
Thence N43°29'21"E for 10.27 Feet to the True Point of Beginning, the area being 0.01 Acres, all in Lane County, Oregon.

Once the legal description is written, you can review it and accept it as it is, or you can edit and save it.


Traverse Closing Points

In the Closure View you can specify the initial point and closing point for a traverse.

TPC treats the initial point as the POB in the legal description.

Areas reported in legal descriptions are always from the initial point to the closing point..

Beginning at a IP thence North 23° 27' East for 163.50 to a IP 3, said point being the True Point Of Beginning;


Point of Commencement

If the traverse includes calls prior to the initial points, the first point in the traverse will be considered the Point of Commencement.

You can also specify a commencement point chain in the Traverse Properties Commencement dialog.

Note: You commencement point chain should be specified either in the traverse or the Traverse Properties Commencement dialog, but not both. If you include the same chain of points in both the Traverse Properties Commencement dialog and the traverse itself, TPC will not be able to generate a legitimate legal description.


Creating a Legal Description From a Traverse

•From the Traverse View, choose Tools | Legal Description Report.

•Choose the options you want from the Legal Description dialog.


Creating Legal Descriptions for Selected Traverses

•From the Traverses Manager, select the traverses you want legal descriptions for and choose Tools | Traverse Report.

•TPC displays the Traverse Report dialog from which you can choose to create legal descriptions for the selected traverses.


Distance and Direction Type

Beginning with TPC Desktop 2013 Release 1, the distance type, distance units and direction type are all derived from the traverse format. If your traverse is formatted to display true bearings, the legal description will be in true bearings. If your traverse units are chains, the legal description will be in chains.

TPC includes the distance and direction information following the traverse name and before the legal description itself. The following example includes ground distance at project elevation of 5,000.

[[ Legal Description: Lot 2 ]] Friday, September 20, 2013 12:03:43
Feet Factor=1.00000000
Ground Dist (at project elevation 5000.00)
Grid Bearing (inverse grid coordinates)
;
thence North 90° East for 285.02 ; ...


Decimals and Rounding

You control the number of decimals for each legal description via the Decimals button from the Legal Description dialog.

The decimal places control the rounding used in the legal description. For example, to display just minutes in directions (i.e. N 4° 20' W), specify 2 for the direction decimals and TPC will round each direction up to the nearest minute.


Area

The area displayed for the traverse is also based on the distance type of the traverse. If the distance type of the traverse, for example, is set to 'ground distance at project elevation', the area computed will be the area at the project elevation and not the grid area.


Related Topics

Legal Description Dialog
Reports
Report View
Message View

Editions

Personal, Premium, Professional

 

 

 

Copyright © 2026 Traverse PC, Inc.