This topic introduces horizontal curves in TPC Desktop.
Horizontal Curves and Spirals in Traverses
In TPC, you enter horizontal curves in traverses. The traverse point sequence defines the geometry of the horizontal alignment. Use direction and distance to create the tangents and use curve data like radius and arc length to create the horizontal curves.
See Alignments Are Defined by Traverses.
Displaying Curve Data
To display curve data in the Traverse View, choose View | Format View... and include the letters R (radius), C (arc length), Q (delta or central angle), c (PC->PR bearing), r (PR->PT bearing) and t (tangent) in the display sequence. Include the letters H (horizontal distance = chord dist) and A or B (chord azimuth or bearing) if they are not already included.
Note: For a curve or spiral segment, the dist and bearing or azimuth displayed in the Traverse View are the dist and bearing or azimuth of the long chord.
Curve Data is Stored with the PT
All curve data is stored with the PT of the curve. To edit a curve, highlight it’s PT and choose COGO | Horizontal Curve or just edit any of the curve data in the same row as the PT.
Entering Horizontal Curves
You typically enter horizontal curves in a traverse as you enter data from a legal description or plat.
The way you enter the curve depends on the geometry of the alignment and the information you have, but typically, you enter what you have and TPC computes and displays the rest.
See Entering Horizontal Curves.
The Horizontal Curve Dialog
The Horizontal Curve dialog is used when you can enter the curve you need to in the Traverse View. For example, if you have an incoming PC->PI direction that is not the same as the preceding course in the traverse.
It can also be used to summarize and report all the information about a single curve, when needed.
•From the Traverse View, highlight any existing curve or any point for which you would like to enter curve data, and choose COGO | Horizontal Curve to display the Horizontal Curve dialog.

•Enter the data you are given, and the dialog box computes the others.
•When you have the curve data you want, choose OK to update the highlighted point in the Traverse View.
As you enter data in the Horizontal Curve dialog, you will notice that the field names change state to indicate which data you have entered. These states indicate which data is given and which data is computed. When you enter a number, the field name becomes depressed to show that data is being held. If a value is computed, its field name is released. To change the state, just click on the field name.
From this dialog, you can create dozens of curves by combining the data you are given. Once you understand the basic operation of the Horizontal Curves dialog box, you can make it work with almost any combination of data you run across.
Saving the Computed PI and PR
PI - Point of Intersection. PR - Point or Radius.
PI and PR points can be included in the Traverse View if that's how you created a curve, but otherwise are not shown.
If you need to create them for use elsewhere in the survey
•Highlight any curve point in the Traverse View and choose COGO | Horizontal Curve.
•Enter point labels for the PI or PR and choose Save PI or Save PR.
TPC will check for existing point labels, ask you to change the labels if necessary and save the points.
When the PI and PR are saved, they become part of the survey even though they may not be used in any traverse. To include them in any of the traverses, recall them by their point labels.
Grid vs Ground / Geodetic
The curve distances and directions displayed in the Traverse View and the COGO dialogs are based on the distance type of each alignment traverse. For example, if an alignment traverse is formatted for ground distance at project elevation, radii, arc and tangent lengths will be ground distance at project elevation.
This gives you the option of working with alignment parameters at ground (use a ground distance type) or grid (use grid distance type).
So if the traverse is displaying 'ground distance at project elevation (3500 ft)', curve data like radius, arc length and tangent length will be displayed as 'ground distance at project elevation (3500 ft)'.
TPC stores the values you enter as raw data. So if you enter a radius of 500', TPC stores 500' as the radius. However, the radius, along with any other raw curve distances, is converted to a grid distance for any internal computations. Spirals do this same thing also.
See Geodetic Alignments.
Related Topics
Entering Horizontal Curves Entering Spirals Creating Stations at Intervals Geodetic Alignments
Editions
Personal, Premium, Professional
|